πŸ—οΈ WAJAALE CITY MEETING HALL Β· LIVE STATUS (27 APRIL 2026)

πŸ“… Construction start: 16 March 2026 | 🏁 Target handover: 10 July 2026 | πŸ’° Total BOQ: 25,731,513 ETB
πŸ“† TODAY: 27 APRIL 2026 β†’ ELAPSED WORKING DAYS & PROGRESS AUTO-CALCULATED
βœ… Real-time simulation based on actual date: elapsed working days = 31 | Progress & earned value reflect today's completion

πŸ“‹ Real-Time Snapshot

πŸ“† Calendar days elapsed43 days (since 16 Mar)
πŸ› οΈ Working days elapsed (Mon–Sat)0
🎯 Overall progress (cost‑weighted)0%
βš™οΈ Current construction phaseβ€”
πŸ“… As of working day0 / 0
⏳ REMAINING UNTIL HANDOVER β€”
πŸ”” Today's status (27 Apr 2026): Steel erection ongoing, substructure complete

πŸ’° Financial & Cost Performance

πŸ“Œ Total budget (excl. VAT)25,731,513 Birr
πŸ’Έ Earned value (actual as of today)0 Birr
πŸ“‰ Remaining budget0 Birr
πŸ“Š Cost performance (EV/Total)0%
🧾 BOQ categories: Substructure | Steel+Roofing | Masonry+Finishes | Electrical | Aluminium

⚠️ Critical Path & Today's Actions

β–ͺ️ 27 April 2026: Working day 31 of 98
β–ͺ️ Steel structure erection at ~20% completion
β–ͺ️ Blockwork preparation in progress
β–ͺ️ All steel materials on site since day 6
β–ͺ️ Substructure (foundations/slab) 100% complete
β–ͺ️ Next milestone: Roofing & aluminium (starts day 48)

πŸ“Š Construction Gantt (as of 27 April 2026) β€” bar fill = % complete

πŸ”— View full interactive Gantt chart β†’

πŸ“‹ Work Packages & Progress (Cost-Weighted BOQ)

Work PackageCategoryStart (day)Duration% Complete (today)
πŸ“ Earned value calculation: Based on actual working days elapsed since 16 March 2026. Today = 27 April 2026 β†’ 31 working days completed (Mon-Sat, excluding holidays). Progress is linear per task schedule.

🏁 Key Milestone Status

πŸ“¦ Steel material arrivalβœ… Completed
πŸ—οΈ Steel truss erectionπŸ”„ In progress
🧱 Substructure (ground slab)βœ… 100%
🎨 Finishing works⏳ Upcoming
πŸ“… Remaining working daysβ€”